The central control system ЦСУ-05 was put into the operation on the Kapitalnaya Mine (Republic of Uzbekistan)

The central control system ЦСУ-05 was put into the operation on the Kapitalnaya Mine (Republic of Uzbekistan)

At the end of January, 2023 the specialists of the «Institute of Mining Electrical Engineering and Automation», LLC completed the supervision and commissioning works of the previously delivered central control station ЦСУ-05 under the contract with JV «INSTITUT GORNOY ELEKTROTEXNIKI I AVTOMATIZATSII», LLC (Tashkent, the Republic of Uzbekistan) for the Capitalnaya Mine (Kochbulak deposit).

The mine specialists were also successfully trained to work with the system by the specialist from the «Institute Of Mining Electrical and Automation», LLC.