IGEA to supply high-voltage cells to Garlyk MPP

The IGEA has made and is going to deliver high-voltage cells to the potassium chloride plant with annual capacity of 1.4 mln ton, located at the Garlyk potash field in the Lebap Velayat, Turkmenistan.
This May we signed an agreement with the general contractor, Belgorkhimprom JSC, and within these three months we produced a set of IGEA S switchgear consisting of thirty-two cells. IGEA S switchgear provide supreme power supply reliability, and easy to install and service, absolutely maintenance-free.
Belgorkhimprom accepted the products and left them in consignment storage at the manufacturer’s, to be sent to Turkmenistan a month later.
It is the third delivery by the IGEA to the Garlyk MPP. Last year we produced a microprocessor based shaft alarm system for its conveyances.